    Jimmy, I just established the a/c proposed is reverse cycle split system.

    If that’s the case, then it still comes under Section 110 (Minor Renovations)  which says this:

    (4)  Before obtaining the approval of the owners corporation, an owner of a lot must give written notice of proposed minor renovations to the owners corporation, including the following—

    (a)  details of the work, including copies of any plans,

    (b)  duration and times of the work,

    (c)  details of the persons carrying out the work, including qualifications to carry out the work,

    (d)  arrangements to manage any resulting rubbish or debris.

    (5)  An owner of a lot must ensure that—

    (a)  any damage caused to any part of the common property by the carrying out of minor renovations by or on behalf of the owner is repaired, and

    (b)  the minor renovations and any repairs are carried out in a competent and proper manner.

    Apart from that, if the strata committee has full delegated powers to act as the OC, then the SC can decide on approval or otherwise and if the owner isn’t happy they can take it to an EGM or AGM  for approval by the entire OC.