#26556
Lady Penelope
Strataguru

    newlsie – Was there a date on the Order whereby the [s62] repairs were required to be made? Have you contacted your Strata Manager and/or SC to remind them of their obligations? I would also be advising the SC that if this is not rectified ASAP then you will take this matter back to NCAT to enforce the Order.

    Below is an extract from the NCAT site.

    “If a work order (to provide goods or services) is made in your favour and the order is not complied with within the period specified by the Tribunal, you can apply to NCAT to renew proceedings. Learn more about applying for a renewal of proceedings.”

    and

    https://www.ncat.nsw.gov.au/Documents/ccd_factsheet_enforcing_orders.pdf

    In some situations pecuniary penalties may apply if Orders are not complied with.