    Thanks! In answer to your questions:

    • Was the work voted upon at a General Meeting of the O/C or by the Executive Committee?

    It was voted on by the O/C as the lowest quote, without knowledge of the connection to the EC chair relationship with the contractor

    • What was the total value of the work?

    Quoted at $64000, an additional $5500 was added after the work was approved but before it commenced.

    • Was the Builder Licensed?

    Yes

    • Was there a Written Contract between the Builder and the Owners Corporation?

    There is no contract on record and the contractor apparently cannot find one.