13/09/2012 at 1:23 am
#16509
My block received a payment from HOW for repairs of defects by the builder. The block is about 12 years old.
the insurance payment was about 3 years ago. the money ahs all been spent. Some defects of the same type that were agreed to be covered in the insurance payment, have since come to light in other units. These units weren’t iidentified in the original scope of works.
is there a standard time limit on variations to a payment for defects under HOW?
thanks