    You’ll find the relevant statement here – it’s the second paragraph under the Headline October 2011 Changes

    In general, home owners must lodge a claim for defective or incomplete building work within the insured period. If the work is defective, the home owner must lodge the claim within 6 months of becoming aware of the problem.

    In your case, that would mean lodging a claim within six months of the inspection report being delivered. This is a NSW regulation.

    JimmyT

    If you want to be alerted when anyone replies to your posts or responds to this topic, please register and login, then you will be able to subscribe to the topic. The opinions offered in these Forum posts and replies are not intended to be taken as legal advice. Readers with serious issues should consult experienced strata lawyers. NB: Longer threads may spill over to additional pages - look for the numbers on the bottom right, under the last post.