    According to the Act:

    initial period, in relation to an owners corporation, means the period commencing on the day on which that owners corporation is constituted and ending on the day on which there are owners of lots the subject of the strata scheme concerned (other than the original owner) the sum of whose unit entitlements is at least one-third of the aggregate unit entitlement.

    In other words, the initial period ends when one-third of units have been sold (give or take a few big or little ones to make up the one-third of Unit Entitlements).  The developer then has two weeks in which to call the first AGM.

    Importantly, at that point the voting power of the developer is reduced to one-third of their holding until such times as they have sold more than half their units. Also, the developers are restricted in contracts that they can sign in this initial period as they all have to be approved (or not)  by the owners at the first AGM.

    If you want to be alerted when anyone replies to your posts or responds to this topic, please register and login, then you will be able to subscribe to the topic. The opinions offered in these Forum posts and replies are not intended to be taken as legal advice. Readers with serious issues should consult experienced strata lawyers. NB: Longer threads may spill over to additional pages - look for the numbers on the bottom right, under the last post.