      Hi,

      Can the S/C vote upon enhancements to a Lot owner’s private property at the expense of the O/C?

      And if so, wouldn’t that enhancement set a precedent with other Lot owner’s who would then expect the O/C pay for similar work? 

      In this instance, the enhancement is to a planter box that is neglected by the owner and as the Lot is at the front of the building – it is an eyesore. Other residents, like myself, pay and tend to their own planter boxes/gardens attached to the Lot.

      How can the O/C address this eyesore with the Lot owner?

      Thank you.

    Viewing 1 replies (of 1 total)
    • Author
      Replies
    • #20878 Reply
      Jimmy-T
      Keymaster

        @LawoftheLand said:
        Can the S/C vote upon enhancements to a Lot owner’s private property at the expense of the O/C? And if so, wouldn’t that enhancement set a precedent with other Lot owner’s who would then expect the O/C pay for similar work? 

        This probably comes under your by-laws plus section 120 (2) of the Act (below).

        Under the standard by-law (12 in the current model by-laws), the owner or occupier of a lot “must not, without the prior written approval of the owners corporation, maintain within the lot anything visible from outside the lot that, viewed from outside the lot, is not in keeping with the rest of the building.”

        You probably have this by-law or something similar.

        Under Section 120 (2), the owners corp (or strata committee) can carry out work that should have been done by an owner and then charge them for it. FYI:  The significant word is “may”, meaning they have the option to do the work and the option to charge for it.

        120 Owners corporation may carry out work required to be carried out by others


        (2) Work required to be carried out under term or condition of by-law

        If a person who is the owner … tenant or occupier of a lot in the strata scheme fails to carry out work that is required to be carried out by the person under a term or condition of a by-law of the scheme, the owners corporation may carry out the work and recover the cost of carrying out the work from that person, the owner of the lot (if the person is not the owner) or any person who, after the work is carried out, becomes the owner of that lot.

        If you want to be alerted when anyone replies to your posts or responds to this topic, please register and login, then you will be able to subscribe to the topic. The opinions offered in these Forum posts and replies are not intended to be taken as legal advice. Readers with serious issues should consult experienced strata lawyers. NB: Longer threads may spill over to additional pages - look for the numbers on the bottom right, under the last post.
      Viewing 1 replies (of 1 total)
      Reply To: Can the S/C vote to enhance a lot owner’s property?
      PLEASE ... If your property is not in NSW, mention its location (state). Don't identify companies or individuals by name. Don't mention or promote your company or services. Keep acronyms and initials to a minimum. Please, don’t use “quote” unless there is a specific point to which you wish to refer, then highlight (define) that specific passage before you click on "quote". Otherwise just use reply. THANKS.

      You can use BBCodes to format your content.
      Your account can't use all available BBCodes, they will be stripped before saving.

      Your information:




      Forums Common Property Current Page