- This topic has 2 replies, 3 voices, and was last updated 7 months, 2 weeks ago by .
-
Topic
-
QLD – We have some very large expenditure – building internal and external painting – occurring in the next few years. How can I be confident the allocated funds reflect market prices? We use a quantity surveyor through our Strata Manager but recent experience shows some of their allocations are wrong eg $18k for intercom replacement of 25 yo system yet lowest quote was $60k inc GST. Or $140k for lift rollers and door replacements that weren’t in the forecast. We have used 2 different quantity surveyors over the past 5 years but get the same forecast and we are assured they are the best around.
Also, should we use estimates with the GST calculated? Currently it is non GST figures which cause issues when owners review it. I understand the BCCM require budgets and forecasts to show real cash outlays the BC will pay.