  • Thanks Chris.  I neglected to couple the builder with the developer…they are “dealing” with the issue in unison (or not). 

    The EC has booked a glass expert for this morning so, with that in hand and following a rigorous clean last week, they will make a full blooded claim on the developer/builder this week. 

    I did not know that the defect notification period is about to be shortened.  How odd.  Why wouldn’t that give shonky operators an opportunity to do work that “will hold for a couple of years”? As far as I know architects can be sued for eons if they make a mistake.  Some building defects (the more substative/expensive ones) can only develop over a significant period of time. Is the CTTT run by builders/developers or was this a brainwave of the last State Government?